Construction process of PE threading pipe

Update:06-08-2019
Summary:

All kinds of PE pipes are generally not cut at the begi […]

All kinds of PE pipes are generally not cut at the beginning of production, so we need to effectively cut them when using PE threading pipes, and reasonable hot-melt welding operations to achieve the needs we need. Layout effect, for PE threading pipe hot melt welding process let us follow us to understand in detail.

1. Welding preparation of PE pipe. Hot melt welding construction preparation work

Install the slips that match the specifications of the PE pipe into the rack; prepare enough support to ensure that the PE pipe to be welded can be at the same height as the center line of the frame and can be easily moved; set the temperature of the heating plate to 200-230 °C. Turn on the welder power, turn on the hot plate, milling cutter and oil pump switch and test run.

2. Check the PE pipe and clean the pipe end → tighten the PE pipe → mill the milling pipe end → check the pipe end misalignment and clearance → heat the PE pipe and observe the smaller crimp height → PE pipe weld and cool to the specified time → remove the PE tube. During the welding process, the operator should refer to the parameters of the welding process card for operation, and if necessary, adjust it according to changes in weather, ambient temperature, etc.:

Check whether the specifications and pressure level of the PE pipe to be welded are correct. Check whether the surface is flawed, bumped or scratched. If the depth of the flaw exceeds 10% of the wall thickness of the PE pipe, it should be used after partial resection; use soft paper or cloth. Alcohol removes oil or foreign matter from the two ends of the pipe; place the PE pipe to be welded in the frame slip, so that the length of the two ends is equivalent to the part of the PE pipe frame, which is supported by the support, so that the PE pipe axis and the machine The centerline of the rack is at the same height, and then fastened with the slips; when inserting the milling cutter, first turn on the power switch of the milling cutter, then close the ends of the PE tube and apply appropriate pressure until there are continuous chips on both ends. , remove the pressure, wait a moment, then retreat the movable frame, close the power supply of the milling cutter; take out the milling cutter, close the two pipe ends, check the alignment of the two ends (the displacement of the two ends of the PE pipe can not exceed 10% of the wall thickness, pass Adjust the straightness of the PE pipe and the elastic slip to improve; the gap between the two ends of the PE pipe should not exceed 0.3mm. If it does not meet the requirements, it should be milled here until the temperature of the heating plate reaches the set value. Rack, imposed by regulations Force, until the smaller curling edge reaches the specified height on both sides, the pressure is reduced to the specified value. After the time is reached, the movable frame is released, the heating plate is quickly taken out, and then the two pipe ends are closed, and the switching time is shortened as much as possible, and cooled to the specified time. After that, relieve the pressure, loosen the slip, and take out the PE pipe that is connected.

3. The welding process parameters are directly related to the welding parameters: temperature, time and pressure.

As an important process of use, it plays an important role in the role of PE threading pipe. We not only need to understand, but also need to focus on the following information, so that we will not use it when we use it. I am very upset about handling things.